Site
|
Contaminant
|
Year Constructed
|
Project summary
|
Target AC
|
Delivery Methods
|
Project Web Link
|
AC Projects Completed in North America
|
USN Hunters Point San Francisco Bay, CA
|
PCBs & PAHs
|
2015
|
1 acre pilot study that includes ca 0.5 acres of SediMite and 0.5 acres of AquaGate+PAC.
|
4 - 6 %
|
Telebelt ®
|
USN Hunters Point Case Study
|
USN Sierra 1B Pier Pearl Harbor, HI
|
PCBs & mercury
|
2015
|
11,000 ft 2 under-pier pilot study with ~ 4,400 ft 2 of SediMite and 4,400 ft 2 of AquaGate+PAC.
|
2.5%
|
Gravity fed hopper with pneumatic conveyance to an under-pier operator who directed the output over specific 10' x 10' cells.
|
USN Sierra 1 B Case Study
|
Mirror Lake Restoration Dover DE
|
PCBs
|
2014
|
Full-scale 4.9 acre remediation of lake and downstream with SediMite.
|
5%
|
Telebelt® in deeper areas of lake; induction air horn, vortex spreaders, and by hand in nearshore
|
Mirror Lake Case Study
|
Puget Sound Naval Shipyard Bremerton, WA
|
PCBs & mercury
|
2012
|
0.5 acre pilot study to evaluate the efficacy of AC application under an active Navy pier. Product was AquaGate+PAC.
|
4%
|
Telebelt ® over-water and under pier sections of the project.
|
PSNS Case Study
|
Berry’s Creek, NJ
|
Mercury & PCBs
|
2012
|
Small test plots (30 x 30 ft) with AC placed on the surface of a phragmites marsh using three approaches: 1) granular carbon only, 2) granular carbon with a 2 inch coarse sand cap, and 3) fine granular carbon in the form of SediMite™. Activated carbon dose was 5 percent by dry weight of sediment in the top 10 cm.
SediMite™ application rate was 5 kg/m2
|
AC 5%
SediMite™ 5 kg/m 2
|
GAC as a slurry using a hydroseeder. Coarse sand was delivered to plot using a telebelt and manually layered over the treatment area. SediMite™ was applied using a Vortex TR Aquatic spreader.
|
EPA, 2013
|
Lower Duwamish Slip 4 Seattle, WA
|
PCBs
|
2011
|
Dredged areas on the banks and riverbed at the head of the slip included a filter layer of well graded sandy gravel, amended with sand-size granulated activated carbon.
|
0.5%
|
Sandy gravel with GAC mixed upland and placed using a dredge bucket.
|
Slip 4 Lower Duwamish Case Study
|
Onondaga Lake Pilot Study Onondaga County, NY
|
Chlorinated benzenes & PAHs
|
2011
|
1 acre capping pilot to demonstrate the implementability of mixing/slurrying GAC and sand on-shore and placing the material over a pre-defined depth and area. The project informed full scale construction planning and implementation.
|
0.25 - 1.0 lb/ft 2
|
Sand/GAC slurry mix system mixed with water and pumped through a pipeline and booster pumps to a hydraylic spreader barge. Slurry placed in a series of parallel lands.
|
Onondaga Lake Pilot Case Study
|
Canal Creek, MD
|
PCBs & mercury
|
2010
|
Twenty-four test plots, each 8 meters by 8 meters to evaluate the performance of three AC applications in a wetland: two pelletized AC products (AquaBlok and SediMite, and a PAC slurry . Pilot project under ESTCP ER-200825 and ER-200835.
|
3%
|
Depending upon the test product, a Vortex spreader, hydroseeder, bark blower, or by hand. Many of the test plots were accessible on-foot, in the submerged wetlands the spreaders were used on a boat.
|
Canal Creek Case Study
|
Naval Air Station, Cottonwood Bay, Dallas TX
|
PCBs, PAHs, chromium, lead
|
2009
|
Small-scale pilot project that tested reactive mats featuring a 0.28 lb/ft2 activated carbon, 0.23 lb/ft2 apatite, 0.28 lb/ft2 organoclay amendment mixture and an AOS 80 geotextile.
|
0.28 lb/ft 2
|
Prototype reactive mats rolled up and deployed from a john-boat by divers. Divers secured the mats in the shallow bay with anchors, anchor screws, and blocks. Some of the treatments were further covered with sand.
|
SERDP ER-1493
|
NAVFAC TR-2366-ENV Technical Repor t
|
Bailey Creek, Fort Eustice, VA
|
PCBs
|
2009
|
Pilot-scale studies of SediMite in 225 m 2 plots within a marsh and in the main channel.
|
5%
|
Vortex spreaders from boat
|
Bailey Creek Case Study
|
St. Louis River Superfund Site Duluth, MN
|
NAPL/PAHs
|
2006
|
11 acres of cap that included a reactive core mat withAC to absorb advected PAH-porewater during consolidation. The cross section of the cap was 0.5 ft (15 cm) sand/activated carbon mat/2.5 ft (75 cm) sand.
|
0.4 lb/ft 2
|
Reactive mats attached to outer sheet-pile wall and unrolled toward shore from a moveable barge. Overlapping RCMs stapled and allowed to sink, followed by sand placement
|
ITRC 2014
|
Olta and Hornday, 2007
|
Grasse River, Massena, NY
|
PCBs
|
2006
|
0.5 acre pilot project with AC mixed into PCB-contaminated sediment.
|
3.2 - 5%
|
Two application methods tested: "roto-tiller" and tine sled. The tiller is an enclosed device that first applied (via spraying) activated carbon onto the sediment surface, followed by mixing of the material into near-surface sediments using the roto-tiller (was used with and without mixing). The tine sled device included direct injection of activated carbon into near-surface sediments.
|
Grass River Pilot Project Web Site
|
Hunters Point 2005 Pilot Project San Francisco Bay, CA
|
PCBs & PAHs
|
2005
|
Pilot project under SERDP-1207 and ESTCP ER-200510.
|
5.1%
|
Two types of GAC applications were tested. In the first, the AC was spread onto the surface of the sediments via a backpack spreader located on an Aquamog and then a rotovator arm mixed the GAC into the sediments. WIth the second applicationGAC was sprayed onto the rotovator and mixed.
|
SERDP-1207
|
ESTCP ER-200150
|
Hunters Point 2005 Case Study
|
Anacostia River, Washington, DC
|
PCBs, PAHs, chromium, lead
|
2004
|
1100 m 2 area was capped with a coke-filled RCM and covered with 15 cm of sand.
|
24 kg/m 2
|
Twelve 3.1 m x 31 m coke-filled RCMs were placed with a 0.3 m
overlap using a crane with a clamshell.A diver followed the unrolling mat to insure proper placement. A sand layer (~15 cm) was then placed above the RCM by particle broadcasting to
|
McDonough et al, 2006
|
ITRC 2014
|
AC Projects Completed in Europe
|
Grenlandsfjords, Norway
|
Dioxins/furans
|
2009
|
Pilot project to demonstrate efficacy of a hydraulic application of AC/clay mixture at depth. Plot size was 40,000 m 2 at a depth of 100 m. Comparative plots also included crushed limestone, and clay-only cpas.
|
2 kg/m 2
|
Dredged clean marine clay was mixed with a coal-derived powdered AC (d80 < 45 μm) in 10:1 dw ratio. To increase the density of the clay + AC slurries the salinity was increased by adding NaCl, and was pre-mixed for at least one hour in the hopper dredger tank to a water content of 56−70% prior to placement. A hopper dredge was used in reverse mode: the intake pipe was as a tremie with the material released approximately 5 m above the seafloor. To facilitate settling the powdered AC was mixed with a 10% w/w
|
Grenlandsfjords Case Study
|
Trondheim Harbor, Norway
|
PAHs
|
2008
|
Pilot project evaluating three treatments: AC, AC+clay, and AC covered with sand for erosion protection. Test plots were 225 m 2
|
5 kg/m 2
|
NaCl in a 100-L cement blender to saturate the AC pore system with water that was slightly heavier than surrounding water. For the AC-only and AC+sand fields, this slurry was pumped out with a flexible manually operated 5 cm hose For the AC+clay field, AC and bentonite were mixed 1:1:6 with 10%-NaCl and pumped out as described above.
|
Trondeheim Harbor Case Study
|
NGI 2011
|